The parcel is at Navarathna Agrahara Village, Jala Hobli, Yelahanka Taluk, Sadahalli, Bengaluru, Karnataka 562157, on survey numbers 7/2, 8, 9/1, 9/3, 10/1, 10/2, 11, 12/2, 92/1, 92/3, 92/4 and 92/5. Mahindra Navrat Sadahalli is being developed by Mahindra Lifespace Developers Limited, the real estate arm of the Mahindra Group, through two wholly owned subsidiaries — Anthurium Developers Limited and Shreyas Stones Private Limited — which assembled the site in two acquisitions disclosed to the BSE in January and June 2025.

01 / Site plan

Mahindra Navrat Sadahalli site plan

Mahindra Navrat Sadahalli master plan site layout showing the ten tower footprints around the central landscaped green, the two clubhouses and the commercial block
02 / Master Plan

What the Mahindra Navrat Sadahalli master plan is, and what it is not

Every figure on this page is proposed. A Terms of Reference application is the first step of environmental appraisal, not the end of it, and this one did not reach a hearing.

Mahindra Navrat Sadahalli is at the pre-approval stage. An application for Terms of Reference (Category B1, proposal no. SIA/KA/INFRA2/582765/2026) was filed with SEIAA Karnataka on 22 June 2026 and was auto-delisted from the PARIVESH portal on 1 August 2026 after the statutory 30-day window to answer the authority's Essential Details Sought lapsed. Delisting is a procedural step, not a rejection — the developer can relist the proposal and restart the appraisal. As of 12 August 2026 no refiled or successor proposal has been filed, and the project has no environmental clearance. RERA registration not yet issued; no K-RERA record found as of 12 August 2026.

So read what follows for what it is: a set of dimensions the developer certified to a regulator, which is a great deal more than a brochure claim and a great deal less than a sanctioned layout. The numbers are checkable. The plan is not approved.

03 / Master Plan

How 17.21 acres becomes 14.74 acres at Mahindra Navrat Sadahalli

The filing does not give one site area. It gives a chain of four, and the difference between the first and the last is the difference between the number in a headline and the number every ratio on this page is actually measured against.

StepAreaIn acres
Total land including footpath and nala kharab69,655.93 sq m17.21 acres (17 Acre 8.5 Guntas)
Less footpath and nala kharab1,062.29 sq m
Area excluding footpath and nala68,593.64 sq m
Less area left out2,638.53 sq m
Available for development65,955.11 sq m16.30 acres (16 Acre 11.92 Guntas)
Net site area59,659.03 sq m14.74 acres

The chain is arithmetically clean down to the developable figure. The last step is not explained. Between the 65,955.11 sq m available for development and the 59,659.03 sq m net site area sits 6,296.08 sq m — 1.56 acres, about 9.5% of the developable area — and the documents in hand do not label it. Karnataka schemes commonly lose a band of that order to road-widening handover and statutory relinquishment, but the filing does not say so and we are not going to say it for the filing.

It matters because the net site area is the denominator. The 56.49% landscape share and the 15.34% ground coverage that follow are measured against 59,659.03 sq m, not against the 17.21 acres in the headline. Anyone comparing this plan with another project's open-space claim should first check which of the four areas that claim is divided by.

04 / Master Plan

The Mahindra Navrat Sadahalli land-use breakdown

ComponentAreaShare of the 59,659.03 sq m net site
Ground coverage (building footprint)9,154.67 sq m15.34%
Landscape33,704.36 sq m56.49%
Driveway and ramp13,000 sq m21.79%
Surface parking3,300 sq m5.53%
Services500 sq m0.84%
Total59,659.03 sq m100%
Civic amenities (stated separately)3,305.37 sq m

Three things about that table are worth saying plainly rather than smoothing over.

It is a genuine partition, not five separate declarations. The five components sum to 59,659.03 sq m — the net site area, to the square metre — and every percentage is the component divided by that area, correct to two decimals. Many filings of this type record land-use figures in different sections of a form that then fail to add up. This one adds up, which means the table can be read as a single pie rather than as five unrelated commitments.

Landscape is arithmetically the residual. Three of the five rows are round figures — 13,000, 3,300 and 500 — while ground coverage is carried to two decimals. Because the five must close on the net site area, landscape at 33,704.36 sq m is the balancing item: everything not under a building, a driveway, a ramp, a surface parking bay or a service structure is booked as landscape. That does not make 56.49% wrong, and it is not a criticism of the filing, which is how these returns are compiled. It does change what the number promises. What it commits to is that a little over half the net site carries no building, no road and no parking. What it does not commit to is that all of it is planted.

Civic amenities sit outside the partition. The 3,305.37 sq m civic amenity reservation is stated on its own and carries no share of the net site in the filing. Since the five land-use components already account for the whole of it, that reservation is not additive to them, and the filing does not say which of the five it falls within.

05 / Master Plan

The Mahindra Sadahalli site plan: 10 towers on 15.34% of the ground

ElementAs proposed in the filing
Residential towers10, lettered A, B, C, D, E, F, G, H, J and K
Residential floors2 Basement + Ground + 22 Upper Floors
Maximum height69.45 m
Commercial blockGround + 3 Upper Floors, 14.95 m
Clubhouse 1Lower Ground + Ground + 1 Upper
Clubhouse 22 Basement + Ground + 1 Upper
FAR achieved2.49
Setbacks16 m
Fire driveways8 m
Total built-up area2,31,478.49 sq m (about 2.49 million sq ft)

The tower lettering runs A, B, C, D, E, F, G, H, J, K. It skips I. That is what the application says and it is reproduced here as filed.

Low footprint is not low density, and the two should not be confused. 1,166 homes on 17.21 gross acres is about 68 homes per gross acre and about 72 per developable acre. By unit count this is a dense scheme and describing it as low density would be wrong. Anyone shortlisting on a search for low density apartments in North Bangalore should read that distinction before this plan is added to the list: what 15.34% ground coverage buys here is open ground, not fewer neighbours. What the scheme is is low footprint — roughly 2.26 acres of building on a 14.74-acre net site. Those are the same decision seen from two directions. The density goes up in height rather than out across the ground, and 22 upper floors at 69.45 m is what pays for the open ground plane.

What 2.49 million sq ft actually measures. FAR of 2.49 on the 59,659.03 sq m net site gives roughly 148,551 sq m of FAR-countable floor area, about 1.60 million sq ft. The filing separately records a total built-up area of 2,31,478.49 sq m, about 2.49 million sq ft. The difference of roughly 82,900 sq m — about 36% of the total — is the part FAR generally does not count: the two basement levels, parking, service floors and plant. That split is our arithmetic on two stated inputs, not a figure lifted from the document. It matters for one reason: the 2.49 million sq ft headline is a construction quantity, not saleable area, and it should never be divided into a price.

The two clubhouses do not share a section. Clubhouse 1 is Lower Ground plus Ground plus 1 Upper. Clubhouse 2 is 2 Basement plus Ground plus 1 Upper — the same basement depth as the towers. A lower-ground level is normally cut into a fall in the ground rather than excavated as a full basement, which suggests the two blocks stand on different parts of the site at different levels. That is a reading of the section, not a statement in the filing. The filing gives storey counts and nothing about where either block sits.

At a stated 16 m setback and a maximum height of 69.45 m, the towers stand roughly four times as tall as the setback band is wide. That is conventional high-rise geometry and it is the reason a scheme of this density can still hold more than half its net site clear of building.

Averaged across ten towers, 1,166 apartments works out to about 117 homes per tower and about 5.3 per upper floor. That is arithmetic on two confirmed inputs. The filing publishes no tower-by-tower distribution and no floor plate, so it is an average and not a description of any actual floor. The unit position is set out on the floor-plans page, where the confirmed area-band split and the inferred configurations are separated from each other.

06 / Master Plan

Open space and green-belt design at Mahindra Navrat Sadahalli

33,704.36 sq m of landscape is 8.33 acres. Against 2.26 acres of building footprint, the planted and open allocation is 3.68 times the ground the buildings stand on. Spread evenly across 1,166 homes it is about 28.9 sq m per apartment, roughly 311 sq ft — our arithmetic, and an even spread is not how landscape is used, but it is a fair way to compare one scheme against another.

The site's wider setting supports the open-space case rather than depending on it. The filing records a land-use context of Commercial, Park and Open Space, and Traffic and Transportation zones, with the land converted for residential use, and it names four adjacent water bodies: the Navarathna Agrahara, Tharabanahalli, Doddajala and Bandikodigenahalli lakes.

One question the filing does not answer, and it is the one that decides what this open space can become. Two basement levels run under ten towers and under Clubhouse 2, and the documents do not state how much of the 33,704.36 sq m sits on natural grade and how much sits over a basement slab. Planting over a slab is a different proposition from planting into soil: soil depth governs whether a green spine grows specimen trees with real canopy or shrubs, lawn and planters. Anyone assessing this plan should ask for the grade-versus-slab split on whatever layout is eventually released, because the same square metres deliver very different shade in twenty years depending on the answer.

07 / Master Plan

Roads, access and circulation

The site plan labels two access points — Navarathna Agrahara road and Sadahalli Gate — and the filing records two existing 18 m roads serving the parcel.

Beyond that, the external road picture is proposed rather than built. The application states a proposed 30 m master-plan road, and states that the existing 18 m Navarathna Agrahara road is being widened to 30 m. Both upgrades are proponent-stated in this project's own Terms of Reference. Neither could be verified as a funded or tendered contract in any public source. That is worth stating without softening, because the external circulation this master plan assumes exists in the developer's own application and, as far as we could check, nowhere else. A scheme of 1,166 apartments plus a Ground plus 3 commercial block and two clubhouses feeding a tertiary 18 m village road is a last-mile question rather than a detail, and the document to ask for is a road notification from the local planning authority, not the drawing inside the application.

Internally, circulation is the second-largest claim on the land after landscape. Driveway and ramp take 13,000 sq m, 21.79% of the net site — nearly a quarter of the ground, and the honest measure of how much of any high-rise master plan is given over to moving and storing vehicles. Fire driveways are stated at 8 m. Parking runs to 1,588 spaces proposed against a statutory requirement of 1,457, a surplus of 131, held across two basement levels beneath the towers plus 3,300 sq m of surface parking at grade; the category breakdown sits on the amenities page. The circulation consequence is the number that matters here: close to 1,600 cars entering and leaving through access onto a single village road.

What the filing does not publish is an internal road hierarchy, gate positions, entry and exit geometry, drop-off arrangements or a basement ramp layout. No source in hand supports a description of any of those, and any diagram showing them today has invented them.

08 / Master Plan

Pedestrian movement and landscaping

There is no published pedestrian plan for Mahindra Navrat Sadahalli. No jogging-track length, no tree count, no planting schedule, no species list and no statement about separating pedestrian from vehicular movement appears in any document available for this project. Pages that quote such details for this project are quoting something that is not on the record.

What the geometry permits can be stated. With 15.34% of the net site under building and 21.79% under driveway and ramp, the balance is a single large allocation — 33,704.36 sq m — rather than fragments left over between blocks, which is enough contiguous ground to carry a continuous walking network between the ten towers and the two clubhouses. Whether the layout does that is a design question, and no layout has been released. The recreational facilities a two-clubhouse development of this size would normally carry are set out on the amenities page, described as planned and without invented sizes or counts.

09 / Master Plan

Below-ground and services infrastructure

Two basement levels run beneath the residential towers and beneath Clubhouse 2, giving the scheme most of its parking without spending ground on it. Services take the smallest land allocation in the plan — 500 sq m, 0.84% of the net site — which is consistent with plant that mostly sits below grade or inside the basement envelope rather than in standalone yards.

Power provision is 8,225 kVA from BESCOM, with diesel generator backup of 500 kVA times four, or 2,000 kVA. Backup at about 24% of connected load is a common-areas-and-essential-services provision — lifts, pumps, lighting, treatment plant — rather than full apartment backup. That is a normal design choice and not a criticism, but it is worth confirming what the generators are actually specified to carry before assuming every flat is covered.

Construction practice recorded in the filing includes reuse of excavated topsoil and of construction debris. On a site with two basement levels under ten towers, the excavation volume is substantial, and what happens to that spoil is a real environmental question rather than a token commitment.

10 / Master Plan

Sustainability infrastructure at Mahindra Navrat Sadahalli

SystemAs stated in the filing
Water requirement922 KLD — 606 KLD fresh, 316 KLD flushing
Sewage treatment plant830 KLD in the resource table; 850 KLD on the final site plan
Treated-water reuseFlushing, gardening, vehicle washing, floor washing, construction and plantation
Rainwater harvestingRoof-water sumps, a storm-water sump and 80 recharge pits
Solid waste3,171 kg/day
Organic waste converter1,275 kg/day
Power8,225 kVA from BESCOM; backup 500 kVA x 4
SolarSolar photovoltaics proposed in the environmental-management documentation

The sewage treatment plant is stated twice, at two different sizes. The Terms of Reference resource table states an 830 KLD sewage treatment plant while the final site plan shows 850 KLD — a discrepancy inside the same filing, which we report as it stands rather than reconcile. It is worth noting where each figure may come from without choosing between them: 830 KLD is exactly 90% of the 922 KLD water demand, which is the conventional sewage-generation factor, and 850 KLD is what that rounds up to as an installed plant size. That observation does not settle which number is right, and we are not settling it. Both are on the record and both are published here.

Water is the variable to press hardest on. 922 KLD across 1,166 homes is about 791 litres per home per day, and that figure also carries the commercial block and the two clubhouses, so the residential share is lower. The context is what makes it significant: this belt sits outside the BWSSB Cauvery network and runs on borewells and private tankers, with Cauvery Water Supply Scheme Stage VI approved but realistically 2028 or later. A declared demand of 922 KLD on a borewell-and-tanker supply is a large commitment, and this plan does not show where the water comes from — only how much of it the scheme expects to use and treat. The supply side is the question to put to the developer in writing, and the amenities page sets out what to ask for.

The reuse network is where the treatment plant and the landscape meet. Flushing demand alone is 316 KLD against a plant of 830 or 850 KLD, so treated water has to find work well beyond flushing — which is what the stated reuse list for gardening, vehicle washing, floor washing, construction and plantation is for, and what 8.33 acres of landscape irrigation absorbs.

Rainwater harvesting is roof-water sumps, a storm-water sump and 80 recharge pits. Eighty pits across 59,659.03 sq m of net site is one recharge pit per roughly 746 sq m, or one for every 14 to 15 apartments.

On waste, 3,171 kg/day across 1,166 homes is about 2.72 kg per home per day. The organic waste converter is sized at 1,275 kg/day, roughly 40% of the total — which is the wet fraction, the part an on-site converter is designed to take. The remaining 60% is dry and hazardous waste leaving the site through municipal and authorised channels, and no filing makes that disappear.

Solar photovoltaics are proposed in the environmental-management documentation. No capacity is stated anywhere, so no capacity should be quoted.

11 / Master Plan

What the Mahindra Navrat Sadahalli master plan does not settle

  • There is no sanctioned layout drawing. The filing gives areas, storey counts and utility loads. It does not give positions — which tower stands where, where the gates are, where the clubhouses sit relative to the towers, or how the open space is shaped.
  • The 6,296.08 sq m between the developable area and the net site area is unlabelled in the documents in hand.
  • The sewage treatment plant is 830 KLD or 850 KLD. Two documents in the same filing disagree and both are published above.
  • How much of the 33,704.36 sq m of landscape sits on natural grade rather than over a basement slab is not stated, and it governs what can be planted.
  • The 30 m road on which external circulation depends is proponent-stated only. No funded or tendered contract for the widening, or for the second proposed 30 m road, could be verified.
  • There is no tower-by-tower unit distribution and no BHK mix. The application gives an area-band split of 1,078 units of 50 to 150 sq m and 88 above 150 sq m, and nothing finer.
  • None of this is approved. The Terms of Reference application was auto-delisted on 1 August 2026, there is no environmental clearance, and RERA registration has not been issued.

Two of those can be rechecked without going through anyone. The environmental file is searchable on the PARIVESH portal under proposal no. SIA/KA/INFRA2/582765/2026, and Karnataka RERA registrations are searchable at rera.karnataka.gov.in — a genuine project registration begins with PRM/KA/RERA/ and contains /PR/. If either record moves, the plan on this page moves with it.

12 / Questions

Mahindra Navrat Sadahalli Master Plan — frequently asked questions

No. RERA registration not yet issued; no K-RERA record found as of 12 August 2026. We checked the Karnataka RERA project registry in full, including the applied-but-unregistered rows the registry also publishes, and there is no entry for this project, for Mahindra Lifespace Developers Limited anywhere in Yelahanka taluk or Jala hobli, or for either land-holding subsidiary. Until a registration number is issued, no booking or allotment can lawfully be taken, and any agent quoting a RERA number for this project is quoting something that does not belong to it.
No. Mahindra Navrat Sadahalli is at the pre-approval stage. An application for Terms of Reference (Category B1, proposal no. SIA/KA/INFRA2/582765/2026) was filed with SEIAA Karnataka on 22 June 2026 and was auto-delisted from the PARIVESH portal on 1 August 2026 after the statutory 30-day window to answer the authority's Essential Details Sought lapsed. As of 12 August 2026 no refiled or successor proposal has been filed, and the project has no environmental clearance.
It is an automatic, machine-executed removal from the portal's active list — not a rejection and not a refusal on merits. Under MoEF and CC Office Memorandum IA3-22/25/2021-IA.II-Part(1) dated 25 October 2024, a proposal whose Essential Details Sought go unanswered for 30 days is auto-delisted, and the developer may relist it once the information is ready. This record shows submission on 22 June 2026 and a system-generated delisting at 3 a.m. on 1 August 2026, which fits that arithmetic exactly. The appraisal can restart; it has not restarted yet, and nothing has been approved.
Navarathna Agrahara Village, Jala Hobli, Yelahanka Taluk, Sadahalli, Bengaluru, Karnataka 562157, at 13.200106 north and 77.638050 east, fronting Navrathna Agrahara Main Road. It is 1.5 km by road from NH-44 at Sadahalli Gate and 9.1 km by road from the airport terminal forecourt. The correct PIN code is 562157, not 562110 — the latter is Devanahalli SO in Bangalore Rural district, a different taluk and district.
Mahindra Lifespace Developers Limited, the real estate arm of the Mahindra Group, listed as MAHLIFE on the NSE and 532313 on the BSE. It assembled the site through two wholly owned subsidiaries: Anthurium Developers Limited took about 8.2 acres in January 2025 with a disclosed GDV of nearly Rs 1,000 crore, and Shreyas Stones Private Limited was acquired outright for Rs 199 crore in June 2025 for about 8.79 acres, with a disclosed GDV of about Rs 1,100 crore. The June 2025 BSE filing names Survey Nos. 10/2, 11 and 12/2 — three of the twelve survey numbers in the environmental filing for this site.

Next step for Mahindra Navrat Sadahalli

Mahindra Lifespaces has published no price and no launch date for Navrat Sadahalli. Register and you will get the configuration sheet, the price list and the K-RERA number the day each is issued.